Chinese New Year factory shutdown calendar
Every February, China stops. Factories close for one to three weeks, ports back up, and freight rates spike. Here is when it happens and when you need to order.
Pick a year
- Chinese New Year
- --
- Official public holiday
- --
- Typical factory shutdown
- --
- Last practical order date
- --
- Production resumes (estimated)
- --
Chinese New Year dates
How the shutdown actually works
| Phase | What happens | Lead time |
|---|---|---|
| Order cut-off | Last date a factory will accept a new production run before the break | 45–60 days before CNY |
| Last production day | Lines stop; workers start travelling home | 5–10 days before CNY |
| Shutdown | Factories closed; offices skeleton-staffed | CNY −7 to CNY +14 days |
| Return ramp-up | Workers trickle back; output at 50–70% for a week or two | 2–3 weeks after reopening |
| Port backlog | Containers queue; rates peak for 3–4 weeks | Through late February |
Frequently asked
How long do Chinese factories close for Chinese New Year?
Plan for two to three weeks of zero output, plus one to two weeks of reduced output afterwards. The official public holiday is usually eight days, but the real shutdown is driven by how far workers travel, not by the legal minimum.
When should I place my order?
For sea freight, place orders at least 60 days before Chinese New Year and book the space 45 days out. For air freight, 30 days is usually enough, but rates spike in the final two weeks.
Do all factories close?
Almost all production facilities do. Some trading companies and warehouses stay partially open, but nothing ships at normal volume. Assume total stoppage unless your supplier explicitly confirms otherwise in writing.
Is it cheaper to order during the shutdown?
There are no goods to buy, but some suppliers offer discounts for orders placed before the break and paid up front, in order to fund the holiday. Those terms are worth negotiating two months out, not two weeks out.